Project Details
- Project Manager: Matt Hood
Scope of Work
Remodels/Additions - $50,000
- Remodel entry to improve security
- Enclose all classrooms
- Remodel health room
Fairness Formula Projects - $387,328
The School Site Improvement Committee identified fairness formula projects - a list of recommended projects. The list will be prioritized and completed as budget allows.
- Audio / Visual - Replace stage curtain and sound system
- Cabinets and Countertops - Install new classroom cabinets and bookshelves
- Exterior Improvements - Improve landscaping
- Exterior Lighting - Outdoor lighting in parking lots for safety
- Flooring - New flooring in gym, art room
- Furniture, Fixtures, and Equipment - New classroom furniture
- Hydration Stations - Replace drinking fountains with hydration stations
- Interior Lighting - Upgrade lighting throughout school
- Restrooms - New toilet partitions
Technology Infrastructure
- Replace hardware that enables wired and wireless connections to the Internet.
In Progress
Remodels / Additions
- Classroom enclosure plus entry addition and remodel: Design in progress and pricing forthcoming. Work anticipated to begin summer 2019
Fairness Formula
- Classroom cabinets: design complete. Work anticipated to be done over summer 2019
Completed Projects
- Replaced hardware that enables wired and wireless connections to the Internet. The front office was excluded to accommodate remodeling work
- New flooring installed in the art room
- New classroom and cafeteria furniture installed
- New toilet partitions installed