Project Details

  • Project Manager: Eldrick Hill

  • Architect: Hord/Coplan/Macht

  • Contractor: Nunn Construction

Overview
 

Set to open in the fall of 2018, Legacy Peak Elementary School—along with adjacent space for the Center for Modern Learning (CML)—is the first project of an 80-acre master planned school site. The elementary school will house 600 preschool through fifth grade students with a learning commons, gymnasium, cafeteria, art, music and flex spaces for 21st Century learning. 

The new building is located at the future intersection of Research Parkway & Wolf Valley Drive.

Project Features

  • PK- 5 elementary school with 24 classrooms for kindergarten through 5th grades and one pre-school classroom

  • After-hours access to the gym, learning commons and cafeteria 

  • Separate entries and parking for each program 

  • Outdoor classroom, playing field, and playgrounds 

  • Separate bus loading area with easy access to Legacy Peak and CML

Completed Projects

  • Ground breaking on May 30, 2017

  • Transfer of land ownership to Academy District 20

  • Land graded

  • Concrete foundation walls poured

  • Both elevator shafts erected

  • Masonry walls for gym completed

  • Curb, gutter, and asphalt placed for west parking lot 

  • Last beam for Legacy Peak placed on October 20, 2017

  • Solar tubes installed in Legacy Peak and CML

  • Exterior masonry completed and windows installed at Legacy Peak

  • Polished concrete floors complete in Legacy Peak and CML

  • Poured asphalt for exterior basketball court

  • Gym LVT floor installed

  • Asphalt completed for entire site

  • Classroom wings (A &C) complete

  • Fire alarm system installed

  • Playground equipment installed

  • Turf field installed

  • All concrete poured at site

  • Sprinkler system installed

  • Wing B (cafeteria, gymnasium, art & library) complete

  • Audio/visual systems installed

  • Landscaping completed for entire site

  • Ribbon cutting ceremony on August 14, 2018