Project Details
Project Manager: Eldrick Hill
Architect: Hord/Coplan/Macht
Contractor: Nunn Construction
Overview
Set to open in the fall of 2018, Legacy Peak Elementary School—along with adjacent space for the Center for Modern Learning (CML)—is the first project of an 80-acre master planned school site. The elementary school will house 600 preschool through fifth grade students with a learning commons, gymnasium, cafeteria, art, music and flex spaces for 21st Century learning.
The new building is located at the future intersection of Research Parkway & Wolf Valley Drive.
Project Features
PK- 5 elementary school with 24 classrooms for kindergarten through 5th grades and one pre-school classroom
After-hours access to the gym, learning commons and cafeteria
Separate entries and parking for each program
Outdoor classroom, playing field, and playgrounds
Separate bus loading area with easy access to Legacy Peak and CML
Completed Projects
Ground breaking on May 30, 2017
Transfer of land ownership to Academy District 20
Land graded
Concrete foundation walls poured
Both elevator shafts erected
Masonry walls for gym completed
Curb, gutter, and asphalt placed for west parking lot
Last beam for Legacy Peak placed on October 20, 2017
Solar tubes installed in Legacy Peak and CML
Exterior masonry completed and windows installed at Legacy Peak
Polished concrete floors complete in Legacy Peak and CML
Poured asphalt for exterior basketball court
Gym LVT floor installed
Asphalt completed for entire site
Classroom wings (A &C) complete
Fire alarm system installed
Playground equipment installed
Turf field installed
All concrete poured at site
Sprinkler system installed
Wing B (cafeteria, gymnasium, art & library) complete
Audio/visual systems installed
Landscaping completed for entire site
Ribbon cutting ceremony on August 14, 2018