Project Details

  • Project Manager: Eldrick Hill
  • Architect: CRP Architects
  • Contractor: Daniel-Barry Construction

Scope of Work

Remodels & Additions - $13,250,000

  • Remove modulars and add 10 new classrooms
  • Stadium remodel
     
  • Swimming pool addition

Fairness Formula - $788,179

The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows. 

  • Carpet replacement
  • Purchase new bleachers
  • Replace gymnasium floor

Facility Audits - $90,000

  • HVAC
  • DDC Upgrades

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet. 

​In Progress

Remodels and Additions

  • 10 classroom addition: Construction in progress. Framing, fireproofing, and electrical work is complete.Drywall, masonry, window installation complete. Flooring, paint, and finishes in progress. Scheduled to be complete in summer 2019

​Work Completed

  • Library renovated and carpet replaced
  • Replaced hardware that enables wireless connections to the Internet. Wired upgrades were also accomplished in the library
  • Security cameras replaced
  • Gym renovation complete