Project Details

  • Project Manager: Eldrick Hill
  • Design Firm: Schendt Engineering | Hall Architects
  • Contractor: Daniel-Barry Construction

Scope of Work

Remodels/Additions - $1,000,000

  • Remodel entry to improve security
  • Add air cooling system

Fairness Formula Projects - $515,780

The School Site Improvement Committee identified fairness formula projects - a list of recommended projects. The list will be prioritized and completed as budget allows.​

  • Update all classrooms; chalkboards
  • Update all bathrooms
  • New windows and blinds
  • Remove asphalt and tiered flower beds
  • New flooring throughout building
  • Paint inside and outside of building
  • Furniture, Fixtures, and Equipment - New furniture throughout school

Facilities Audit - $390,000

  • Replace windows

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet

​In Progress

Remodels / Additions

  • Remodel entry: design complete. Work scheduled to be done over summer 2019
     

​Completed

  • Air conditioning installed in classrooms
  • New cabinets, cubbies and countertops installed in classrooms
  • Chalkboards replaced with markerboards in classrooms
  • New carpet installed in classrooms
  • Replaced hardware that enables wired and wireless connections to the Internet