Project Details
Project Manager: Matt Hood
Architect: FBT Architects
Contractor: GH Phipps Construction
Scope of Work
Remodels/Additions - $5,050,000
Create more parking
10-classroom addition
Fairness Formula Projects - $556,000
The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows.
Audio / Visual - Theater upgrades (LED light and sound)
Outdoor seating (bleachers at athletic fields)
Exterior Improvements - Outdoor classrooms
Gym upgrades (floor and A/V system)
Furniture, Fixtures, and Equipment - Replace science lab table tops with acid / heat resistant finishes
Add hand dryers in bathrooms
Storage
Technology Infrastructure
Replace hardware that enables wired and wireless connections to the Internet.
Replace security cameras
In Progress
Remodels/Additions
10-classroom addition and parking lot: earthwork and utility relocation complete, concrete curbs and footers poured, preliminary parking lot asphalt poured, masonry and structural complete, and duct work installed. Stud wall and roofing installation finished. Roof top unit and windows to be installed next. Furniture order placed for installation in late summer 2019
Fairness Formula
Outdoor classrooms: furniture designs in progress and determining scope of landscape work with selected contractor. Work anticipated to be complete over summer 2019
Business Enterprise Initiative space: design in progress. Work anticipated to be completed over summer 2019
New science table tops: order done for replacement over summer 2019
Library shelves: new shelving units ordered and will be installed in April
Completed Projects
New media platform installed in gym
New stage lights installed in theater
Gym A/V system upgraded
Security cameras replaced
New projectors installed
New exterior storage container installed
New theater house lighting system installed