Project Details
Project Manager: Dan Moors
Scope of Work
Remodels/Additions - $2,075,000
Remodel to add auditorium; relocate Challenger Learning Center to the Center for Modern Learning
Gymnasium; construct additional storage space for auxiliary gym
Fairness Formula Projects - $1,155,506
The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows.
Finish installing air conditioning in rooms without
Audio / Visual
Basketball Backboards - Electric / motorized basketball standards
New flooring throughout the building including small gym
Furniture, Fixtures, and Equipment
Hydration stations to replace drinking fountains
New bathroom stalls
New window coverings (blinds) throughout the building
Facilities Audit - $60,000
ADA access to track and field
Technology Infrastructure
Replace hardware that enables wired and wireless connections to the Internet
In Progress
Remodels/Additions
Auditorium: Construction documents complete. Work scheduled to begin in summer 2019
Entry remodel: Construction documents complete for redesign of existing Challenger Learning Center space to accommodate school admin area. Work scheduled to begin in summer 2019
Fairness Formula
Restroom upgrades: Work scheduled to occur over summer 2019
Flooring: Work scheduled to occur over summer 2019
Completed Projects
Removed old TVs and installed ceiling mounted projectors in classrooms.
ADA access to field complete
Replaced hardware that enables wired and wireless connections to the Internet