Project Details
Project Manager: Eldrick Hill
Architect: Hord/Coplan/Macht
Contractor: Nunn Construction
Overview
Set to open in the fall of 2018, the Center for Modern Learning (CML)—along with the adjacent space for Legacy Peak Elementary — is the first project of an 80-acre master planned school site. The CML features learning spaces for the Academy Online High School, Journey K-8, Home School Academy, as well as Coding, Cybersecurity, and Robotics, plus the Challenger Leaning Center.
The new building is located at the future intersection of Research Parkway & Wolf Valley Drive.
Project Features
Separate entries and parking for the CML, Challenger Learning Center, and Legacy Peak Elementary
Outdoor classroom, playing field, and playgrounds
After-hours access to the Legacy Peak gym, learning commons and cafeteria
Separate bus loading area with easy access to the CML
Completed Projects
Ground breaking on May 30, 2017
Transfer of land ownership to Academy District 20
Land graded
Concrete foundation walls poured
Both elevator shafts erected
Masonry walls for gym completed
Curb, gutter, and asphalt placed for west parking lot
Last beam for the Center for Modern Learning placed on November 29, 2017
Solar tubes installed in Legacy Peak and CML
Polished concrete floors complete in Legacy Peak and CML
Poured asphalt for exterior basketball court
Gym LVT floor installed
Asphalt completed for entire site
All concrete poured for entire site
Sprinkler systems installed for entire site
Playground equipment installed
Temporary Certificate of Occupancy secured on August 8, 2018
Nunn Construction turned over control of building to District 20
Landscaping completed for entire site
Elevator installed
Audio/visual systems installed
Ribbon cutting ceremony on August 14, 2018