Project Details
- Project Manager: Eldrick Hill
Scope of Work
Remodels/Additions
- Remodel entry to improve security
- Renovate front office for safety and efficiency
Fairness Formula Projects - $230,128
The School Site Improvement Committee identified fairness formula projects - a list of recommended projects. The list will be prioritized and completed as budget allows.
- Furniture, Fixtures, and Equipment
- Audio / Visual
- Remove wallpaper and paint walls in all hallways
- Reface old / broken countertops and cabinets
- Renovate bathrooms with eco-friendly, motion sensor flushers and faucets and replace stalls
- Basketball Backboards - Install automatic basketball standard systems in gym
- Replace work carpet and tile throughout the building
- Exterior Signage - Purchase and install digital marquee
- Gym Curtain - Install new stage / gym dividing curtain
Facilities Audit - $200,000
- Upgrade electrical capacity
Technology Infrastructure
- Replace hardware that enables wired and wireless connections to the Internet
In Progress
Fairness Formula:
- AV: install new projectors in classrooms. Work scheduled to be complete over summer 2019
Facilities Audit:
Upgrade electrical capacity: parts ordered and delivered. Scheduled for completion over summer 2019
Completed Projects
- Gym stage lighting control box replaced
- Replaced hardware that enables wired and wireless connections to the Internet
- Entry remodeled to improve security
- Bathrooms upgraded