April 22, 2019

Students and teachers held their first day of classes in the new permanent home for the School in the Woods opened. The ribbon-cutting ceremony took place on April 26.

Jan. 14, 2019

A bond-funded Learning Management System, Schoology, launched for teachers, staff, students, parents and guardians. Schoology is an online platform that supports instruction and collaboration.

Aug. 14, 2018

A ribbon cutting ceremony was held for Legacy Peak Elementary and the Center for Modern Learning.

June 18, 2018

Work began at the site for the new permanent home for the School in the Woods.

May 20, 2018

Construction began on the district’s newest middle school, Chinook Trail, as well as the 10-classroom addition at Pine Creek High School.

Nov. 1, 2017

Together with GE Johnson Construction and RTA Architects, the district held the ceremonial groundbreaking for the new permanent home for the School in the Woods.

Sept. 27, 2017

Together with Bryan Construction, RTA/MOA Architects and La Plata Communities, the district held the ceremonial ground breaking for its newest middle school, Chinook Trail.

Sept. 8, 2017

The School in the Woods new fiber connection went live.

Aug. 10, 2017

Academy District 20 completed the installation of fiber optic network to Edith Wolford Elementary School.

June 1, 2017

Academy District 20 awarded two contacts: GE Johnson Construction and RTA Architects for the design/build of a new permanent home for the School in the Woods and Bryan Construction Inc. and RTA/MOA for the design/build of the new Chinook Trail Middle School.

May 30, 2017

Together with Nunn Construction, Nor’wood Development Group and Hord Coplan Macht Architects, the district held the ceremonial ground breaking for Legacy Peak Elementary School and the Center for Modern Learning.

Building Fund

The Building Fund team oversees the procurement, design and construction phases of all the projects included in the 2016 Bond including new construction, remodels and additions, facilities audits, technology infrastructure and discretionary spending.

Building Fund

Overview
The Building Fund team oversees the procurement, design and construction phases of all the projects included in the 2016 Bond including new construction, remodels and additions, facilities audits, technology infrastructure and discretionary spending.
Phone
(719) 234-1562
Hours
8 a.m. - 4:30 p.m., Monday - Friday
Location
Education and Administration Center
1110 Chapel Hills Dr.
Colorado Springs, CO 80920