Project Details
- Project Manager: Eldrick Hill
Scope of Work
Remodels/Additions
- Remodel entry to improve security
Fairness Formula Projects - $255,539
The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows.
- Modulars
- Overhaul the library into a flexible, collaborative learning space
- Fix, replace and update all boys' and girls' bathrooms
- Audio / Visual
- Replace worn carpet throughout the building
- Add playground equipment for older students and replace the surface
- Furniture, Fixtures, and Equipment - Refit classrooms with collaborative, multi-purpose furniture
- Interior Lighting - Improve instructional lighting
Facilities Audit - $85,000
- Fire alarm upgrades
Technology Infrastructure
- Replace hardware that enables wired and wireless connections to the Internet.
In Progress
Fairness Formula
- Library renovation: work scheduled to be complete over summer 2019.
- Restroom renovation: work scheduled to be complete over summer 2019
Technology Infrastructure
- Internal wiring: Work anticipated to be complete in July 2019
Completed Projects
- Resurfaced playground with Rubber Max Mulch
- Repaired exterior walls of modular classrooms
- Upgrades to modulars' walls and flooring and exterior improvements
- Fire alarms upgraded
- Entry remodeled to improve security