Project Details
- Project Team: Project Manager
- Eldrick Hill: Architect
- LKA Partners: Contractor
- Nunn Construction:
Scope of Work
Remodels/Additions - $6,250,000
- Complete Remodel to the interior of Building "B"
- Remodel Library to 21st Century in Building "D"
- Stadium improvements
Fairness Formula Projects - $2,464,703
The School Site Improvement Committee identified fairness formula projects - a list of recommended projects. The list will be prioritized and completed as budget allows.
- New bleachers for gym
- Flooring
- Furniture, Fixtures, and Equipment - New student desks / tables / chairs
- Hydration Stations - Update water fountains
- Paint classrooms
- Additional storage for classrooms
- Update bathrooms
- Synthetic turf for stadium
- Update auditorium and gym audio visual system
- New windows
Facilities Audit - $582,000
- HVAC - Controls DDC upgrades
- Replace sections of roof
- Replace doors and storefront at main entrance
Technology Infrastructure
Replace hardware that enables wired and wireless connections to the Internet.
In Progress
Fairness Formula
- Building A remodel and new flooring: Work scheduled to be complete over summer 2019
Completed Projects
Replaced hardware that enables wired and wireless connections to the Internet. Building B was excluded because it will receive new hardware during remodeling:
- Replaced sections of roof
- Wireless microphones procured
- Audio/visual upgrades in gym, yoga room and cafeteria complete
- Theater lighting upgrade complete
- New furniture installed
- New turf field installed
- Library renovation to 21st century complete
- Four restroom renovations complete
- Engineering classroom remodeled
- Auditorium carpet replaced
- Auditorium stage floor refinished
- Building B remodeled
- Building B roof overlay completed